The house constructor Sekisui House announced on 15th that the company had completed the construction of megasolar facilities at its five factories and had started operation.

The five factories and their rated capacities are as follows:
-Tohoku Factory (Shikama town, Miyagi) 693kW
-Kanto Factory (Koga city, Ibaraki) 2,438kW
-Shizuoka Factory (Kakegawa city, Shizuoka) 1,982kW
-Hyogo Factory (Kato city, Hyogo) 371kW
-Yamaguchi Factory (Yamaguchi city, Yamaguchi) 1,199kW
Total: 6,683kW